PROJECT:
Big 190 Well Pad Site, EQT
DETAILS
Client Name: EQT
Delivery: General Contractor
Location: Wetzel County, WV
Completion Date: 2012
Cost: $2.5 million
Engineer: L & W Enterprises, Inc.
OVERVIEW
Construction of 6,300 foot long access road, drill pad with two drill pits, 1.9 million gallon flowback pit, and a 5.1 million gallon completion pit. Access road was constructed on the side of a very steep hillside through a heavly treed site. Had 1 week to drop 50 acres of trees due to environmental restrictions and then had a very aggressive turn over date for a unique location. Project completed in 6 weeks.
